Home Page | 2007 Report Verification | 2003–2007 Performance | List of references | Your contacts
Links to other Sites | Rössing's Business - 2007 | Rössing Management | Message from MD | People
Communities | Sustainable development | Economic viability | HSE Policy | Chamber of Mines of Namibia | Product Stewardship
Environmental Stewardship | Asset use resource stewardship | Corporate Governance | Mining Uranium & Nuclear Fuel Cycle

 

 

Home › Asset Use Resource Stewardship

ASSET USE RESOURCE STEWARDSHIP


Mining

The year 2007 was an exciting one for Mining. New employees were successfully introduced in order to ramp up from 19 million tonnes mined in 2006 to 31 million tonnes mined in 2007, and to prepare for a further ramp-up to 48 million tonnes.

A number of new equipment items were commissioned in 2007, including two Komatsu PC5500 shovels, a Caterpillar 994 front-end loader, eight 730E Komatsu haul trucks, a Pit Viper production drill, and two D10T track dozers, while one GD120 production drill and a Marion 201M shovel underwent a major overhaul.

Although the business focused on expansion and growth, Rössing’s foundation is to ensure continued uranium production in order to satisfy long-term uranium supply contracts with global customers. Thus, while waste stripping was continued, ore mining concentrated in the eastern sections of the pit. The waste rock removed increased from 16.8 million tonnes in 2006 to 21.4 million tonnes in 2007, while 12.6 million tonnes of ore were processed. In 2007, 571 tonnes less uranium oxide were produced, compared with the 2006 production year. This was mainly attributed to a 21% drop in ore grade.

In the mining area, a number of challenges had to be overcome. As the pit has significantly deepened and narrowed in the last few years, it took longer to get from pit bottom to ground level. Manoeuvring haul trucks with large turning circles becomes more difficult the narrower the pit bottom gets. Also, more water than before was found in blast holes at the lowest mining bench, making blasting increasingly difficult. Consequently, less material was produced in similar time spans.

Processing

The Processing Department is responsible for extracting the uranium from the mined rock, producing uranium oxide, and securely packing and shipping the product to converters overseas for further processing. In the Processing Plant, for example, the Life-of-Mine Extension Project includes upgrading the outdated electrical systems over the next four to five years, upgrading the systems that prevent expensive resins going to waste, and upgrading the dust extraction systems to reduce air emissions of silica-bearing and radioactive dust. Planning, studies and preparation for these projects continued during 2007.

In 2007, work also continued in respect of testing the feasibility of an ore-sorting pilot plant. The plant aims to make the sorting of waste rock from uranium-bearing rock more efficient
by using radiation-scanning techniques.

The Metallurgical Laboratory was refurbished and upgraded to the required standard in 2007. Independent auditor, customer and consultant reports highlighted the improved performance in the laboratory.

Engineering

The introduction and implementation of the Asset Management Improvement (AMI) Project throughout the mine was the year’s principal challenge. This project first assessed the mine’s status quo, and then analysed the gap between the status quo and the mine’s estimated future position. A road map was then developed to chart the course ahead.Both Processing Plant and Mining Operations personnel will focus on fully implementing the ‘Operating for Reliability’ lessons learnt as part of the AMI Project. This will improve the way we manage our assets, and will, in turn, increase productivity and equipment life.

The Maintenance teams also focused on improving defect elimination and the reliability engineering aspects of asset management. The aim is to eliminate repeat failures and look at ways of improving and optimising asset management so that equipment availability and the reliability continue to improve. This will ultimately assist in meeting production targets, and the AMI Project will be instrumental in achieving this goal.

“As a local supplier, Rössing’s extension has also meant an extension of our working activities – thus, a continuity of work. We could retain our skills in our workforce, because it’s normally very difficult to retain skills if one operates on a short-term contract basis. Rössing sets a very high standard: you can’t bring anyone in on your workforce and put them straight to work. It takes a lot of time, training and coaching to get people to the right standard, and once people are in your team, you want to retain them. For us, that has been the most important impact: to retain our workforce and develop them by offering a longer work period. The new mines in the Region have also impacted on us – negatively, on the one hand, since we have lost some of our workforce to other operations; but, on the other hand, it also brings more people to the Region, into the area of skills, and I think with all of us doing the development and training, it’s good for the industry and the regional workforce. It also diversifies the focus. In the past everyone was focused only on Rössing. Now, people are also focusing on Langer Heinrich, Trekkopje and Valencia. Rössing can now share suppliers, share resources, and as an industry one can get better service from your suppliers because there is more to go around for everyone. We have a memorandum of understanding with Valencia that, when they do start mining, we will be their mining partner. However, Rio Tinto is a preferred client of ours – we’ve done several projects for them, in South Africa and Madagascar as well. Rio Tinto and Rössing subscribe to world best practices and that’s what we aspire to as well – that’s why we enjoy working with Rössing. We have set our standards to meet the standards of Rössing. Thus, if and when we do work with other mines in the area and in Namibia, this is the standard that we take with us, lifting the industry standard as a whole.”

GARETH BOOTH
Area Manager, Basil Read Mining Namibia

 

“The Mining Department increased the total tonnes of ore mined in 2007 by 50% compared with the previous year. The Mining team responded well to the challenges, which included the introduction of new people, mining in very confined areas, and commissioning a lot of new mining equipment.”

WERNER EWALD
Manager: Mining

“Considerable progress has been made in 2007 in recruiting graduate metallurgists, foremen and operators to deal with the many challenges in the Processing Department. The overall objective of the Department is to excel in various fields, mainly the processing of ore, consistently achieving targets and producing more than 4,000 tonnes of uranium oxide annually, undertaken without compromising our occupational health, safety and environmental standards.”

BERNARD MORWE
Manager: Processing

“The strong planning and scheduling foundation laid under the Asset Management Improvement principles has already shown some fruitful benefits.”

SHAMBWEKA CIKWILILWA
Manager: Engineering

“2007 has been a year of consolidation in the Projects environment. It is trusted that this consolidated structure can be used as a foundation to build the required skills to accommodate the future for Rössing’s project management.”

ANDRÉ GENIS
General Manager: Engineering Projects


In addition to new equipment delivered to the mine, several mining operations equipment underwent major overhauls.

Engineering projects

In respect of programmes and finances – with consolidation of the Life-of-Mine Extension Project – 2007 was a busy year. The total amount approved for this project is N$772 million, excluding the funds required for the Aligning Business Systems (ABS) upgrade, and of this amount, 78% had been committed by the end of 2007 in completing 55 of the 85 sub-projects. Of the remaining project funds, approximately 76% will be utilised in 2008, 18% in 2009, and 6% in 2010 in order to complete the electrical upgrading of the mine.

A study was done in 2007 on optimising and upgrading the Fine Crushing Circuit. The expenditure of funds was approved and the project awarded. This project will be implemented in 2008 and the challenge will be to attain the planned production, as the construction phase is estimated to take several months.

One of the projects identified previously – and an important part of the Life-of-Mine Extension Project – is the building of an Acid Plant to provide the sulphuric acid required to extract the uranium from the ore. The relevant feasibility study has been completed and a contractor to build the plant will be selected. The EIA is also in its final stages of review.

The project is to be submitted to the Group Investment Committee in 2008 for approval of funding. Work still outstanding is the handling of raw materials, such as sulphur, at the Port of Walvis Bay.

In the recently completed Strategic Production Planning exercise, the need to further expand the mine’s production capacity was identified. The method being investigated for this expansion is heap leaching.

The project is to test the process by building a heap leach test site. The preliminary designs of the heap leach test pads have been completed and approved. Funds are to be obtained for the implementation of the project in 2008.

In 2008, the Department will focus on building capacity to handle critical projects, and align the processes with the changes brought about by the Aligning Business Systems.

 

Home Page  | Contacting us  | Links to other sites  | Legal Notice  | Site Map
Copyright © 1999 - 2008 Rössing Uranium Mine