|
|
|||
|
ECONOMIC VIABILITY Financial Reporting The Business Controls Department was re-established in 2007. The company is in a growth phase and, as a result, there is a need to ensure that its financial controls are strong. This function involves following up on any financial control weaknesses identified internally. Rössing is operating in a competitive environment and, as such, the focus on cost optimisation is imperative. One of the challenges being faced is raising the level of cost consciousness in the organisation. Reporting of actual performance compared against the planned output is one of the ways that this awareness is achieved. After four years in which the company made little or no profit, 2006 and 2007 saw increased profits – with a resultant increase in company tax paid. Value planning Value Planning is a new department that was instituted at Rössing in early 2007 to provide ongoing assistance in identifying and achieving the best long-term production plan. Since approval of the Life-of-Mine Extension Project in December 2005, Rössing has been working towards getting production back to the originally designed capacity, and has been investigating a host of expansion options. This requires a rigorous process for quantifying the value of various initiatives in order to prioritise projects and justify capital The development of such a process and evaluation The main challenges faced by Value Planning during The challenge was addressed by two key initiatives:
|
“2007 was a challenging year for Business Controls, as a majority of the team were new to Rössing. Consequently, the year was about obtaining knowledge of the business so that business controls could be allowed to contribute significantly “A key challenge for Rössing in 2008 and going forward is the risk of an insufficient supply of critical inputs to the U3O8 process that could impact production. Immediate concerns are shortages of power and acid, with water an additional concern for expansion. Value Planning are completing the feasibility study for a new Acid Plant that will lower supply risk and cost of both acid and power through the utilisation of excess heat to drive a steam turbine. In addition, the Department is intimately involved with other initiatives geared towards ensuring power and water risks are mitigated.” “The main focus in 2008 for Long-term Planning is to continue to upgrade the planning model so as to provide more accurate plans.” |
||
|
Planning and technical services: Long-term planning In 2007, infill drilling in the SK (exploration area) and SJ (existing open pit) deposits took place at an increased pace. Unfortunately, this activity was marred by poor safety performance by the drilling contractor. Several steps were taken to correct this and improved performance is expected. The feasibility study for the SK4 project is nearly completed, and mining in the area is expected to commence there in mid-2008. Drilling will move ahead at a rapid pace in both the SK and SJ areas in 2008, with added emphasis on safety in this operation.
|
|||
Home Page Contacting us Links to other sites Legal Notice Site Map |
|||